METALROOFINGINSTALLATIONGUIDEAP PANELMANUAL
10STANDARD PARTS
11PRODUCT DESCRIPTION•24" Coverage•26 GaugeFor color selections,please request a color chart.Galvalume Plus (20 Yr. WARRANTY)Limited Paint Warran
Details are subject to change without prior notice.12STANDARD FASTENER LOCATIONS AT PANELWARNING! Mueller trim comeswith a protective film coating toa
Zone FASTENER SUBSTRATE90ON CENTERSPACING100ON CENTERSPACING110ON CENTERSPACING120ON CENTERSPACING130ON CENTERSPACING140ON CENTERSPACINGZone 1 #12-11
Details are subject to change without prior notice.14IMPORTANT INFORMATIONOIL CANNINGFOAM INSTALLATIONAnti Oil Canning on AP Panel24"What is Oil
15Details are subject to change without prior notice.DETAIL LOCATOR147283596DETAIL SECTION Page1 Eave . . . . . . . . . . . . . . . . . . . . . .152 G
INSIDECLOSURE1. Install the eave trim by sliding it underneath the underlayment and securing it to the roof surface withwafer head screws on 5’ center
INSIDECLOSURE17STANDARD EAVE TRIM INSTALLATION WITH GUTTERDetails are subject to change without prior notice.1. Install the eave trim to the substrate
18STANDARD ADJUSTABLE GABLE & STRIP INSTALLATIONDetails are subject to change without prior notice.WAFER HEAD SCREWSAPPLIED THROUGHBUTYL TAPE 12&q
19STARTING AND ENDING PANEL INSTALLATIONDetails are subject to change without prior notice.Starting Panel1. Apply adjustable strip as previously instr
TABLE OF CONTENTS2Preparation Requirements and Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3Safety Considerations . . . .
20HIGH SIDE RESIDENTIAL EAVE TRIM INSTALLATIONDetails are subject to change without prior notice.1. Attach the high side trim (#0803) to the fascia wi
21VALLEY PANEL AND TRIM INSTALLATIONDetails are subject to change without prior notice.1. Start at the low end, trim and place the valley flashing. Th
STANDARD RIDGE ROLL and HIP INSTALLATIONDetails are subject to change without prior notice.1. Lay a piece of the #0221 ridge roll or hip in position,
23ENDWALL TO ROOF FLASHING INSTALLATIONDetails are subject to change without prior notice.1. Insert the endwall flashing (#0725) behind the existing w
24SIDEWALL FLASHING INSTALLATIONDetails are subject to change without prior notice.1. Apply butyl tape to the bottom side of the J-closure.2. Install
25ROOF PITCH CHANGE INSTALLATIONDetails are subject to change without prior notice.1. Apply lower panels.2. Install the transition flashing (#1487) ma
26STANDARD PANEL ENDLAPDetails are subject to change without prior notice.1. Ensure the lower panel is installed completely (except for the top fasten
The uphill flashing will be 4” wider than the width of thecurb (2” on each side). Cut an 1/8” slot in the two uphillcorners of the panel slightly wide
28CHIMNEY INSTALLATIONDetails are subject to change without prior notice.CHIMNEY FLASHING - SIDEFLASHING - VENTProcedures:1. Trim the opening in the f
Mueller’s #1, 26 gauge, AP Panelshave received the Underwriter’sLaboratory UL2218 ApprovedClass 4 Premium RatingM-APMANUAL-REV. 11/12FIND OUT MORE ABO
This detail & installation manual has been provided to serve as a basic guideline for installing the Mueller AP panelroof system. This manual shou
4
As with all major construction projects, safety should be a primary concern. The erector or contractor should be surethat all OSHA safety rules are fo
Delivery: Mueller takes every precaution to ensure that material is delivered to the customer damage-free and fully protected fromthe elements during
Storage: It is recommended that sheets be kept coveredand out of the elements if at all possible. If sheets are tobe stored outside, the following pre
8STANDARD PARTSDetails are subject to change without prior notice.Note: If using treated lumber, specialcorrosive resistant screws are required.Ask yo
STANDARD PARTS9